Item |
Process |
Responsible Office/Individual |
1 |
Identify the need for an Expert; obtain Budget/Office Management approval; and identify COR |
Requestor |
2 |
Provide high-level notification to budget/acquisition office of the type of expert needed, COR assigned, estimated value and estimated need by date |
Requestor |
3 |
Assign a CO; reach out to customer; provide resource materials; and start tracking |
Acquisitions Branch |
4 |
Identify your expert; estimate the cost range; and validate availability of funds |
Requestor/COR |
5 |
Begin acquisition planning (preparing initial drafts of acquisition package) |
Requestor/COR |
6 |
Prepare and submit unfunded request (UFR), if required |
Administrative Officer/Budget Team |
7 |
Assess COR training requirements and conduct training, if required |
COR |
8 |
Finalize list of desired experts and notify acquisitions/CO |
Requestor/COR |
9 |
Coordinate with Expert regarding SAM registration requirements and alternate methods |
Requestor/COR |
10 |
Review/consider/work on SAM requirements |
Expert Witness |
11 |
Finalize acquisition planning (finalize all acquisition documents) |
Requestor/COR |
12 |
Create and submit purchase request and secure funding |
Administrative Officer/Budget Team |
13 |
Add work to the acquisition queue; manage the queue; prioritize work; and await available Contracting Officer |
Acquisitions Branch |
14 |
Finalize SAM registration determination with Expert: a. Expert will complete SAM registration prior to award. (No deviation) b. Expert will complete SAM registration, but not prior to award. (Temporary deviation) c. Expert will not complete SAM registration. (Full deviation) |
Contracting Officer |
15 |
Review acquisition package; build contract folder; obtain expert pricing/proposal information; and inform COR of progress |
Contracting Officer |
16 |
Create draft contract in _________ |
Contracting Officer |
17 |
Create contract file documentation (including Determination and Findings (D&Fs), fair and reasonable price determinations, etc.) |
Contracting Officer |
18 |
Draft SAM deviation memorandum; obtain OGC review/concurrence; and obtain approval (required only if temporary or full SAM deviation is necessary) |
Requestor/COR (for drafting & internal approvals) Contracting Officer (for external review/approvals) |
19 |
Perform quality control review of draft contract |
Acquisitions Branch |
20 |
Send contract to Expert for review; negotiate any terms and conditions; obtain signatures; distribute contract; record award in FPDS and issue COR Appointment Letter |
Contracting Officer |
21 |
Ensure SAM registration has been finalized and verified (required only if temporary SAM deviation is necessary) |
Contracting Officer |
22 |
Manage the contract |
COR/Expert Witness |
*Necessary for temporary and full SAM deviations
*Necessary for temporary SAM deviation only